Under clause 2.1, the contractor is required to carry out the works in a proper and workmanlike manner. In earlier versions of the SBC/Q there was no mention of this particular clause. However, this was changed in response to the case of Greater Nottingham Co-operative Society Ltd v Cementation and Others (1988). The outcome of this case had potential implications for the relationship between the employer and contractor. During this appeal, an important statement was made that, if there had been a contractual obligation on Cementation to carry out their subcontract works with due care, then it was accepted that Cementation, for breach of that contractual term, would be liable for the economic loss suffered by the Society. (Griffiths 2010, p.245) In recognition of this case, the JCT introduced a new requirement into the SBC/Q in the form of clause 2.1; The Contractor shall carry …(short extract)

+1 862 207 3288