1. In your own words describe what a “Critical Path” is. For the work in this schedule list the activities that are on the critical path.
2. What will happen to the schedule if the “Interior” work takes 40-days to complete?
3. What risk does the contractor have for completing the project after the final completion date (list at least 3.)
4. If the “Site Improvement” work is delayed by the owner due to mistakes in the drawings – will the contractor have a legitimate claim for a time extension? Why or why not?
5. The “Foundation” work is scheduled to be completed during July in Nampa (Nampa isn’t a wet city). This work is delayed for several days due to a rain storm. Does the contractor have a legitimate claim for a time extension? Why or why not (be specific)?
6. Refer to question 5: is this potential delay claim compensable?