PROJECT PLANNING AND CONTROL

PROJECT PLANNING AND CONTROL

COURSE ASSESSMENT 2

Late Penalty System

This module is being delivered through the Manchester Blackboard virtual
learning environment.
All assessments must be submitted through Blackboard at:
http://online.manchester.ac.uk/
If you have any technical difficulties using blackboard, please visit our
support pages at: http://www.studentnet.manchester.ac.uk/blackboard

Submitting your Assignment

1.  Assignments  should  be  typed,  10  or  11  point  font  size  (Times  Roman  or  similar  if
possible) double spaced with a 4 cm margin on the right side of the page with the
page size specified as UK A4. All pages must be numbered.

2.  Assignments  should  be  submitted  in  Microsoft  Office  Project  format  (.mpp,  etc.).  File
names  should  be  kept  simple  and only  contain  alphanumeric  characters  (a-z0-9),
spaces and underscores (e.g. Valid_filename_1.doc). Files with other characters such
as apostrophes, brackets or commas may not be accessible by markers.

3.  Assignments may be uploaded only once; substitutions are not permitted and students
should therefore ensure that the version uploaded is their final submission.

4. Please  ensure  you  include  your  student  number  and  the  assignment  reference
(PPC/Student Number/Jul14/2) in all submitted assignments and that assignments
are paginated. Failure to do this may lead either to a grade not being assigned or being
wrongly assigned

5.  If you are experiencing any difficulty in uploading your assignment to Blackboard, please
email  a  copy  of  the  assignment  and  a  screenshot  of the  error  message immediately  to
your local centre/Student Adviser.

IMPORTANT: ALWAYS RETAIN A COPY OF YOUR ASSIGNMENT

WARNING: Once submitted no substitute assignments will be allowed

Please ensure you include your student number and the assignment reference (PPC/Student
Number/Jul14/2) in all submitted assignments and that assignments are paginated. Failure to
do this may lead either to a grade not being assigned or being wrongly assigned
CASE #4 THE DEVELOPMENT OF A PERT NETWORK DIAGRAM AND ITS
COMPUTATION
IMPORTANTLY, this case assignment will be assessed and the submission
deadline is 5 October 2014, Sunday (23:55 Beijing time)

Following  Case  3,  when  developing  the  schedule  of  the AEC  project,  the  time  estimates  of
some activities are found to appear uncertain. The following table provides optimistic, most
likely, and pessimistic time estimates of the uncertain activities of the AEC project.

No
Activity Name
Optimisti
c Time
(days)
Most
Likely
Time
days)
Pessi
mistic
Time
(days
)
Uncertainties
1  Project proposal
development and its
approval (being merged
into the whole Airport
Expansion Project)
180
210
270  The uncertainty in
obtaining the approval
2  Project feasibility study
and its approval (being
merged into the whole
Airport Expansion
Project)
180
210
270  The uncertainty in
obtaining the approval
3
Land acquisition and
clearance
120
150
210  The uncertainty in
negotiating the
compensation and
resettlement with the
related residents or the
companies
4  Preliminary design and
its approval  (being
merged into the whole
Airport Expansion
Project)
300
330
390  The uncertainty in
obtaining the approval
5  Construction site
preparation
30
30
30  No uncertainty
6  Construction drawing
design  90  90
90  No uncertainty
7
Bidding for the
construction and basic
installation
45
60
90  The uncertainty in
handling the complaints
according to the
tendering law
8  Piling  45  45  45  No uncertainty
9
Earthwork and
foundation works
60
75
90  The uncertainty caused
by the bad weather,
e.g., rainstorm, tropical
storm, typhoon
10  Reinforced concrete  60  60  60  No uncertainty
Please ensure you include your student number and the assignment reference (PPC/Student
Number/Jul14/2) in all submitted assignments and that assignments are paginated. Failure to
do this may lead either to a grade not being assigned or being wrongly assigned
works
11  Roof works  45  45  45  No uncertainty
12  Basic installation
(electrical wiring,
plumbing, drainage,
sewer, etc.)
45
45
45  No uncertainty
13  Interior decoration
works
330
330
330  No uncertainty
14  The works of the
outdoor ground and road
90
90
90  No uncertainty
15  Technical need
identification for the
power supply and
distribution system
90
90
90  No uncertainty
16
Bidding for the power
supply and distribution
system
45
60
120  The uncertainty in
handling the complaints
according to the
tendering law
17  Manufacturing and
delivery for the power
supply and distribution
system
120
120
120  No uncertainty
18  Technical need
identification  for the
boiler and water
treatment equipment
90
90
90  No uncertainty
19
Bidding for the boiler
and water treatment
equipment
45
60
120  The uncertainties in
handling the complaints
according to the
tendering law and in
procuring the imported
goods
20  Manufacturing and
delivery for the boiler
and water treatment
equipment
90
120
150  The uncertainty in the
delivery of long
distance
21  Technical need
identification for the
cooling tower
90
90
90  No uncertainty
22
Bidding for the cooling
tower
45
60
120  The uncertainty in
handling the complaints
according to the
tendering law
23  Manufacturing and
delivery for the cooling
tower
120
120
120  No uncertainty
24  Technical need
identification for the
centrifugal water chillers
90
90
90  No uncertainty
Please ensure you include your student number and the assignment reference (PPC/Student
Number/Jul14/2) in all submitted assignments and that assignments are paginated. Failure to
do this may lead either to a grade not being assigned or being wrongly assigned
25
Bidding for the
centrifugal water chillers
60
60
150  The uncertainties in
handling the complaints
according to the
tendering law and in
procuring the imported
goods
26  Manufacturing and
delivery  for the
centrifugal water chillers
90
120
150  The uncertainty in the
delivery of long
distance
27  Technical need
identification for the
water pumps
90
90
90  No uncertainty
28
Bidding for the water
pumps
45
60
120  The uncertainty in
handling the complaints
according to the
tendering law
29  Manufacturing and
delivery for the water
pumps
120
120
120  No uncertainty
30  Technical need
identification for the
chilled water storage and
distribution system
90
90
90  No uncertainty
31
Bidding for the chilled
water storage and
distribution system
45
60
120  The uncertainty in
handling the complaints
according to the
tendering law
32  Manufacturing and
delivery for the chilled
water storage and
distribution system
120
120
120  No uncertainty
33  Technical need
identification for the fire
extinguishing system
90
90
90  No uncertainty
34
Bidding for the fire
extinguishing system
45
60
120  The uncertainty in
handling the complaints
according to the
tendering law
35  Manufacturing and
delivery for the fire
extinguishing system
120
120
120  No uncertainty
36  Technical need
identification for the
premises distribution
system
90
90
90  No uncertainty
37
Bidding for the premises
distribution system
45
60
120  The uncertainty in
handling the complaints
according to the
tendering law
Please ensure you include your student number and the assignment reference (PPC/Student
Number/Jul14/2) in all submitted assignments and that assignments are paginated. Failure to
do this may lead either to a grade not being assigned or being wrongly assigned

38  Manufacturing and
delivery for the premises
distribution system
120
120
120  No uncertainty
39  Technical need
identification for the
electric power
monitoring system
90
90
90  No uncertainty
40
Bidding for the electric
power monitoring
system
45
60
120  The uncertainty in
handling the complaints
according to the
tendering law
41  Manufacturing and
delivery for the electric
power monitoring
system
120
120
120  No uncertainty
42  Technical need
identification for the fire
alarm system
90
90
90  No uncertainty
43
Bidding for the fire
alarm system
45
60
120  The uncertainty in
handling the complaints
according to the
tendering law
44  Manufacturing and
delivery for the fire
alarm system
120
120
120  No uncertainty
45  Technical need
identification for the
cable system
90
90
90  No uncertainty
46
Bidding for the cable
45
60
120  The uncertainty in
handling the complaints
according to the
tendering law
47  Manufacturing and
delivery for the cable
system
120
120
120  No uncertainty
48  Technical need
identification for the
boiler monitoring system
90
90
90  No uncertainty
49
Bidding for the boiler
monitoring system
45
60
120  The uncertainty in
handling the complaints
according to the
tendering law
50  Manufacturing and
delivery for the boiler
monitoring system
120
120
120  No uncertainty
51  Technical need
identification for the
integrated monitoring
system
90
90
90  No uncertainty
Please ensure you include your student number and the assignment reference (PPC/Student
Number/Jul14/2) in all submitted assignments and that assignments are paginated. Failure to
do this may lead either to a grade not being assigned or being wrongly assigned
52
Bidding for the
integrated monitoring
system
45
60
120  The uncertainty in
handling the complaints
according to the
tendering law
53  Manufacturing and
delivery for  the
integrated monitoring
system
120
120
120  No uncertainty
54  Technical need
identification for the
multi-connected unit air
conditioning system
90
90
90  No uncertainty
55
Bidding for the multi-connected unit air
conditioning system
60
60
150  The uncertainties in
handling the complaints
according to the
tendering law and in
procuring the imported
goods
56  Manufacturing and
delivery for  the multi-connected unit air
conditioning system
90
120
150  The uncertainty in the
delivery of long
distance
57  Technical need
identification for the
installations of the
specialized equipment
and systems
90
90
90  No uncertainty
58  Bidding for the
installations of the
specialized equipment
and systems
45
60
90  The uncertainty in
handling the complaints
according to the
tendering law
59
The installations for the
specialized equipment
and systems
210
240
270  The uncertainty in the
timely payment because
of the financial pressure
of the client/owner
60
The commissioning for
the specialized
equipment and systems
30
45
90  The uncertainty in
getting the power
supply and the water
supply of meeting the
commissioning
requirement
61
Completion and
preliminary check
15
30
45  The uncertainty in the
improvement to meet
all the technical and
operational
requirements
62  Completion and final
check
30
30
30  No uncertainty
63  Project handover  75  75  75  No uncertainty
64  Ready start-up  0  0  0  No uncertainty
Please ensure you include your student number and the assignment reference (PPC/Student
Number/Jul14/2) in all submitted assignments and that assignments are paginated. Failure to
do this may lead either to a grade not being assigned or being wrongly assigned

QUESTIONS
1.  Which  uncertainties  need  to  be  considered  when  you make  the  schedule  of  the  AEC
project?
2.  Develop  the  optimistic,  pessimistic  and  expected  Gantt  chart  and  network  diagram,  and
compute the optimistic, pessimistic and expected start time of the AEC project using MS
Project if the progress objective of the AEC project is 31 March 2013. Discuss if there is
any  change  of  the  critical  path  from  the  optimistic  network  diagram  to  the  pessimistic
network diagram.
3.  Compute  the  project  finish  times  with  low  risks,  base-risks  and  high  risks  by  using  MS
Project  plus  RiskyProject  (download  RiskyProject  Professional  from
http://www.intaver.com  and  also  read  http://www.intaver.com/index-projectmanagementforeducation1.html: the students may download 30-day trial licenses).
(This question is for your further study and you are NOT required to submit the answer
to this question)
4.  Compare your answers for the
1st
,
2nd
and
3rd
question with those given by Mr. He; find the
differences and discuss each difference.(You are NOT required to submit the answer to
this  question  and  you  are  required  to  do  this  question  after  you  submit  your  answers  to
Questions 1, 2 and 3.)

THE REFERENCE ANSWERS OF CASE 2

1.  Develop  your  OBS  (Organizational  Breakdown  Structure)  corresponding  to  all  activities
developed in Case 1.

The  Headquarters  is  first  broken  down  into  the  departmental  level  and  then  further  broken  down
into  the  next  level,  for  example,  the  OBS  component  “Architectural  Planning  and  Design
Department  (APDD)”  is  further  broken  down  into  “The  manager  for  the  project  proposal
development and feasibility study”, “The manager for the architectural design”, etc., and the OBS
component  “Equipment  Department  (ED)”  is  further  broken  down  into  “The  manager  for  power
supply and distribution systems”, “The manager for boilers and water treatment equipment”, “The
manager for cooling towers”, etc. The graphical representation of the OBS of the Shanghai Airport
Construction Headquarters is shown as follows.

Figure 4 The graphical representation of the OBS of the Shenz Airport Construction Headquarters

2.  Develop your RACI Matrix to show the relationships of the WBS (developed in Case 1) and the OBS.

The RACI Matrix of the project of the AEC is shown in the following table.

1
Pre-project preparation

Project proposal development and its approval (being merged into the
whole Airport Expansion Project)
C  R/A
Project feasibility study and its approval (being merged into the
whole Airport Expansion Project)
C  R/A    I                I

Land acquisition and clearance
C    R/A                  I
Preliminary design and its approval    (Being merged into the whole
Airport Expansion Project)
C  R/A    I                I

Construction site preparation
C                    R/A
2
Construction and basic installation

Construction drawing design
R/A    C                C

Bidding for the construction and basic installation
R/A  C    C                C

Piling
C                    R/A

Earthwork and foundation works
C                    R/A

Reinforced concrete and structure works
C    C                R/A

Roof works
C    C                R/A

Basic installation (electrical wiring, plumbing, drainage, sewer, etc.)
C    C                R/A

Interior decoration works
C    C                R/A

The works of the outdoor ground and road
C                    R/A
3
The installations for the specialized equipment and systems

3.1
Power supply and distribution system

Technical need identification for the power supply and distribution
system
C    R/A

Bidding for the power supply and distribution system
I  C    R/A
Manufacturing and delivery for the power supply and distribution
system
R/A                I
3.2
Boiler and water treatment equipment

The WBS and Activities
Department

A
Technical need identification    for the boiler and water treatment
equipment
C    R/A

Bidding for the boiler and water treatment equipment
I  C    R/A
Manufacturing and delivery for the boiler and water treatment
equipment
R/A                I
3.3
Cooling tower

Technical need identification for the cooling tower
C    R/A

Bidding for the cooling tower
I  C    R/A

Manufacturing and delivery for the cooling tower        R/A                I
3.4
Centrifugal water chillers

Technical need identification for the centrifugal water chillers
C    R/A

Bidding for the centrifugal water chillers
I  C    R/A

Manufacturing and delivery    for the centrifugal water chillers
R/A                I
3.5
Water pumps

Technical need identification for the water pumps
C    R/A

Bidding for the water pumps
I  C    R/A

Manufacturing and delivery for the water pumps        R/A                I
3.6
Chilled water storage and distribution system

Technical need identification for the chilled water storage and
distribution system
C    R/A

Bidding for the chilled water storage and distribution system
I  C    R/A
Manufacturing and delivery for the chilled water storage and
distribution system
R/A                I
3.7
Fire extinguishing system

Technical need identification for the fire extinguishing system
C    R/A

Bidding for the fire extinguishing system
I  C    R/A

Manufacturing and delivery for the fire extinguishing system
R/A                I
3.8
Premises distribution system

Technical need identification for the premises distribution system
C    R/A

Bidding for the premises distribution system
I  C    R/A

Manufacturing and delivery for the premises distribution system
R/A                I
3.9
Electric power monitoring system

The WBS and Activities
Department

Technical need identification for the electric power monitoring
system
C    R/A

Bidding for the electric power monitoring system
I  C    R/A
Manufacturing and delivery for the electric power monitoring system
R/A                I
3.10
Fire alarm system

Technical need identification for the fire alarm system
C    R/A

Bidding for the fire alarm system
I  C    R/A

Manufacturing and delivery for the fire alarm system
R/A                I
3.11
Cable system

Technical need identification for the cable system
C    R/A

Bidding for the cable system
I  C    R/A

Manufacturing and delivery for the cable system        R/A                I
3.12
Boiler monitoring system

Technical need identification for the boiler monitoring system
C    R/A

Bidding for the boiler monitoring system
I  C    R/A

Manufacturing and delivery for the boiler monitoring system
R/A                I
3.13
The integrated monitoring system

Technical need identification for the integrated monitoring system
C    R/A

Bidding for the integrated monitoring system
I  C    R/A

Manufacturing and delivery for    the integrated monitoring system
R/A                I
3.14
Multi-connected unit air conditioning system
Technical need identification for multi-connected unit air
conditioning system
C    R/A

Bidding for multi-connected unit air conditioning system
I  C    R/A
Manufacturing and delivery for multi-connected unit air conditioning
system
R/A                I
3.15  Bidding and installations for the specialized equipment and
systems

Technical need identification for the installations of the specialized
equipment and systems
R/A    C                C
Bidding for the installations of the specialized equipment and
systems
R/A  C    C                C
The WBS and Activities
Department

3
No.                                                                                          PFD  APD
D
LD  ED  ISD  OGE  HR
MD
LDA
B
SSD  EDF
A
ED
TA
ED
CS
A

The installations for the specialized equipment and systems
C    C                R/A

The commissioning for the specialized equipment and systems
C    C                R/A
4
Completion and check

Completion and preliminary check
C    C            R/A

Completion and final check
C    R/A    I      I  C
5
Handover and start-up

Project handover
R/A    I        C

Ready start-up
R/A    I        C

The WBS and Activities
Department

3.  Compare the OBS and RACI Matrix developed by you with those developed by Mr. He; find
the differences and discuss each difference.
(Self-discussion)