The Pert Mustang Case Study
Using the Pert Mustang Case Study
1. Assume 45 working days are available to to completed the project including transporting the car to Detroit before the auto show begins. Your report should briefly discuss the aspects of the proposed new business such as the competitive priorities that Roberts asked about
2. Construct a table containing the project activities using the letter assigned to each activity the time estimates, and the precedence relationships from which you will assemble the network diagram.
3. Draw a network diagram of the project determine the activities on the critical path and the estimated slack for each activity.
4. Prepare a project budget showing the cost of each activity and the total for the project. Can the project be completed wit