Project Management

Question 1: (20)
Discuss the management of the scope at the different phases of the project life cycle. Discuss the unique problems associated with the scope in each phase and the tools and techniques used to address those problems. What is the project manager’s role in the management of the scope in each phase?

Question 2: (20)
What is the triple constraint and why is it such an important concept in project management?

Question 3: (20)
Discuss four aspects of the difference between leadership and management, specifically in the context of a project manager’s role on a project.

Question 4: (20)
Consider the following table of activities:

Activity Predecessor Duration
(days)
Start None None
A Start 2
B A 2
C A 4
D B, C 2
E D, F 4
F C 4
G F 3
H E,G 3
End H None

1. Draw the network diagram
2. Complete the forward and backward passes.
3. What activities are on the Critical Path?
4. Which activities have slack?
5. Which activities have free slack?
6. The customer asks to have the project finished in 15 days. Write a short letter describing your recommended options.

________________________________________________________________

Question 5: (20)
Consider the project plan in the diagram below. The vertical dotted lines represent monthly project milestones. There is a major milestone shown as the triangle at the end of month 3, which is where the project is now.

The critical path is A, F, G, …. (red). All modules are planned to consume $1,000 worth of labor. At the month 3 milestone, A, B, F and G have been completed on schedule. Activity C has 4 deliverables and 3 have been successfully completed.

The actual costs for the modules are A = $1,010, B = $1,160, C = $1,270, F = $990, G = $880. The total cost of the project is $10,000.

You are the project manager. Write a report to your stakeholders describing the status of the project at the end of month 3.