project network analysis
In a project network the critical path is the sequence of activities which has the:
most nodes
greatest variance
longest time
most events
most activities
2.
In project network analysis, “slack” refers to the difference between:
latest and earliest times
optimistic and pessimistic times
mean and modal times
finish and start times
observed and predicted times
3.
Activity C has an early start time of 8, an early finish time of 12, a latest start time of 13, and a latest finish time of 17. Its slack is:
1
0
4
5
9
4.
Activity J has a duration of 7 and an earliest finish time of 21. If J’s latest start time is 16, this must mean that J’s slack is ________.
1
3
7
2
4