1. Introduction
The complexity and unpredictability of construction contracts inevitably means that delays are frequent (Pickavance 2005), with delay being defined as:
An act or event that extends the time necessary to finish activities under a contract, (Stumpf 2000).
The prevalence of construction project overruns is worrying high with estimates ranging from 40% (Lowsley & Linnett 2006) to 70% (Groves and Rowe 1999). The employer may have calculated the revenue from the project commencing on a specific date, and this date may be crucial in terms of the schedule of repayment of the project finance, meaning a delay of only a week could be a risk for the project. Delays can be caused by both employer and contractor, and in this piece the issue of the granting of extension time will be analysed in three differing scenarios.
2. Project A.
Here the contractor was on-course to …(short extract)

+1 862 207 3288 